Construction Project

Eatonville High School Track and Field Project Timeline

August 2025

August 18, 2025 – Notice to Proceed
Eatonville School District received official notice to proceed on the long-awaited Track and Field Project.

August 19, 2025 – Construction Begins
Heavy equipment arrived and construction officially began with site preparation. Work started on the track, field, and stadium grandstands.

August 20, 2025 – Early Progress
Crews began excavation, marking the start of a major transformation for our athletes and community.

August 22, 2025 – Track Removal
The old track surface was cleared, bringing the project one step closer to a brand-new facility.

August 27, 2025 – Excavation Underway
Excavation and foundation work continued. Thank you to our community for your continued support and patience.

August 28, 2025 – Aerial View
Special thanks to teacher Erik Swartout for capturing drone footage highlighting the progress.

September 2025

September 1, 2025 – Groundwork Preparation
Crews excavated and hauled dirt in preparation for new drainage systems.

September 2, 2025 – Approvals and Demolition
Final approvals for installation and excavation were received. The Town also approved demolition of the stadium structure and restrooms, allowing work to move forward quickly.

September 4, 2025 – Field Preparation
Surveying equipment was on site. Asphalt was removed from the old end zone, and dirt and rock removal continued.

September 10, 2025 – Curbing Begins
With excavation complete, curbing installation began.

September 22, 2025 – Grandstand Demolition
The stadium grandstands that stood for decades were removed. A bittersweet milestone and an exciting step forward.

September 23, 2025 – Debris Removal Support
Thank you to LeMay Pierce County Refuse and Land Recovery Incorporated for hauling and properly disposing of stadium debris.

September 26, 2025 – Excavation Complete
Demolition and excavation were completed. Crews transitioned to curbing and drainage preparation.

October 2025

October 2, 2025 – Drainage Installation
Catch basins were installed and perimeter curbing continued.

October 7, 2025 – Curbing Nears Completion
Curbing work wrapped up as the project remained on schedule.

October 14, 2025 – Fencing Begins
Fencing installation began around the stadium.

October 16, 2025 – Lighting Upgrades
Old light poles were removed to prepare for new energy-efficient LED lighting.

October 21 to 23, 2025 – Field Events Preparation
Crews prepared pole vault and javelin areas and began installing new LED light poles and fixtures. Thank you to Ohop Mutual for supporting this upgrade.

October 28, 2025 – Pole Vault Run-Up
Concrete pour for the pole vault run-up was completed.

October 29, 2025 – Stadium Foundation Work
Crews continued work on the foundation for the future stadium.

November 2025

November 13, 2025 – Turf Preparation
Grading and leveling began in preparation for turf installation.

November 24, 2025 – Stadium Footings
Work progressed on the new 1,224-seat stadium. Field work continued and stadium footings took shape.

November 26, 2025 – Turf Arrival
Turf materials arrived on site as foundation work continued.

December 2025

December 2, 2025 – Concrete Pour
Crews poured 80 yards of concrete for the next phase of construction. Three members of the cement team were proud EHS graduates helping build the facility they once competed on.

December 2, 2025 – Evening Update
All concrete for 22 footings and piers was poured in a single day.

December 4, 2025 – LED and Turf Prep
Crews prepared foundations for new LED lights and installed pads for the turf field.

December 10, 2025 – Turf Rollout Begins
Turf installation officially began, and preparation for light pole foundations continued.

December 17, 2025 – Retaining Wall Materials
4,000-pound ecology blocks arrived to build a strong retaining wall.

December 19, 2025 – Field Branding
CRUISERS lettering was rolled into the end zone, with Eatonville lettering to follow. Retaining wall blocks continued to be placed.

December 30, 2025 – Year-End Progress
Retaining walls behind the future grandstands were underway. Grandstand assembly was scheduled to begin in January. Turf details including end zone lettering, center field EC, and stitched hashmarks were completed.

January 2026

January 5, 2026 – Grandstand Delivery
Five semi-trucks delivered major grandstand components to campus.

January 6, 2026 – Fabrication and Field Details
Grandstands fabricated in Texas arrived for assembly. Soccer lines were hand-sewn into the turf using colored fibers.

January 12, 2026 – North and South End Work
North end zone preparation continued while unsafe rock was removed from the south end to prepare for a retaining wall and improved emergency and vendor access.

January 13, 2026 – Retaining Wall Materials Arrive
Blocks arrived for the south end retaining wall near the bus loop.

January 14, 2026 – Aerial Views
Additional aerial photos were captured by Erik Swartout.

January 15, 2026 – LED Lighting Installed
New LED lights were installed, improving visibility and reducing long-term energy costs.

January 18, 2026 – Light Poles Installed
Four new LED light poles were installed.

January 19, 2026 – Turf Infill Process
Grandstand bases were installed. Sand infill was worked into the turf fibers, with crumb rubber next.

January 29, 2026 – Grandstand Assembly Begins
Grandstand assembly officially began. Work also continued on the pole vault runway, entry area, discus, and javelin runways.

February 2026

February 2, 2026 – Press Box Installed
The press box was set into place in an impressively fast process.

February 4, 2026 – Fence Replacement
Approximately 185 feet of old fencing was replaced with new material thanks to Quality Fence and community volunteers.

February 18, 2026 – Stadium Update
Roof installation began on the press box, and new goal posts were installed. The stadium continues to take shape as the project moves toward completion.


Project Background

Originally slated to begin in May 2025, the project was delayed due to Governor’s Executive Order 21-02, which required an additional compliance review. With acceptance of the $1.2 million Recreation and Conservation Office (RCO) grant, the district committed to following all requirements to ensure the project meets state standards.

Although Eatonville athletes will play home football games in Yelm this season, the wait will be worth it. By next fall, we will welcome students, athletes, and fans to a state-of-the-art facility that will serve our community for many years to come.

We are grateful for the continued patience and support of our students, families, and fans. Final approval for the replacement stadium is near, and additional details will be shared as the project continues to progress.